Skip to content

Gremista Underground Cable and Grid Supply Point

The Gremista underground cable and grid supply point project has connected Shetland to the electricity grid for the first time, allowing the Island to take advantage of the renewable power generated on the Island. 

Project overview

The project consisted of two distinct sections: the Underground Cable (UGC) element and the grid supply point (GSP). 

The team installed ducting and cabling to carry three sections of new double circuit 132kV UGC between Kergord substation GIS Building and the new Gremista Supply Point substation. These circuits are designated KG and KG2.  

  • Section one: runs from Kergord substation for approx. 6km to a new wood pole.  
  • Section two: connects two wood poles, approx. 1km apart.  
  • Section three: runs between a two new wood poles, to the Gremista GSP, for approx. 4km. 

The ducting and cabling for the project runs circa 11km through environmentally sensitive areas of peatland and the Sandwater Loch.  

The works at the new Gremista substation was undertaken using a new platform created as part of the mobilisation works. The activities required to construct the new substation include:  

  • Construct two grid transformer buildings including 132kV/ 33kV transformers and associated 132kV AIS equipment.  
  • Construct the control building including control room, 33kV GIS hall, Telecom room, metering room, battery room and welfare facilities. 

Customer:

SSEN Transmission

Location:

Shetland Islands

Date:

September 2025

Fun fact: Shetland is the northernmost part of the UK and is actually closer to Norway than mainland Scotland!