Burnt Oak Station Step-Free Access
Delivering step-free access at Burnt Oak station through a new passenger footbridge, lift and upgraded station systems.

Project overview
The Burnt Oak Step-Free Access project has reached another major milestone, following the completion of the detailed design phase and successful mobilisation of the site for delivery.
Working closely with London Underground, and supported by our wider project team and supply chain, we achieved an efficient mobilisation, with processes and controls in place from day one. Since then, the team has successfully completed a major station closure, with Burnt Oak reopening on schedule. During the closure, the new platform opening for the future step-free access lift and walkway was created, alongside the temporary works needed for construction to continue safely while the station remains open to passengers.
The project will deliver step-free access by constructing a new passenger footbridge and a lift from the station concourse, helping to make passengers’ journeys easier, safer and more inclusive. We will also upgrade the Mechanical, Electrical and Public Health (MEP) systems, alongside communications integration systems.
There is also an important community aspect. The project will strengthen connections to local services, jobs and businesses, creating lasting value for the wider Burnt Oak community.